125 MMSCFD Capacity Dehydration Plant at
Mari Field
MGCL installed and commissioned 125 MMSCFD
capacity Dehydration Plant at Mari D&P lease
area in December 2009 to provide 109 MMSCFD
to two “IPP” Independent Power Producers
namely Foundation Power Company (Daharki)
Limited and Star Power Generation Limited.
The plant utilizes TEG as medium to remove
moisture and is equipped with State of the
Art PLC based control system. MGCL
professionals are fully trained and equipped
to achieve the set goal of on specification
gas supply to its customers.
|
15 MMSCFD Capacity Dehydration Plant
(Koonj-1A)
After discovery of Koonj Gas Field in
2008, as an operator of Sukkur Block MGCL
obtained approval of EWT from GOP and
started activities to bring this gas on
production on fast track basis. Laying of 13
KM gas line, construction of surface
facilities and installation of 15 MMSCFD
capacity Dehydration plant was carried out
after GSA with M/s SNGPL.
EWT operations commenced on January 28, 2010
after site acceptance test of Dehydration
plant. EWT was suspended on February 20,
2010 due to unexpected increase of H2S
contents in gas against permissible limit of
agreed in GSA.
Joint Venture of the block after evaluating
various options selected Amine Sweetening
technique to reduce H2S concentration.
Consignment has been received and its
installation and commissioning is in final
stages. It is expected that the EWT
operation will resume in the last week of
September 2011.
|
|
Bhit Shah X-1
MGCL offered drilling services of Mari Rig-1 to
M/s PPL in Hala Block where it carries 35%
working interest and won the contract in open
bidding. This is the 1st ever venture of MGCL to
work as drilling contractor outside MGCL
operated blocks. The well has reached it TD @
3730 m on August 09, 2011. The well is under
logging and testing. |
|
Halini X-1
MGCL as an operator with 65% working interest in
Karak Block with MOL (Joint Venture partner with
35% interest) is in final stages of drilling /
testing of 5350 meter well. The TD has been
achieved in 201 days with Schlumberger Rig-25.
Testing of various promising zones shall be
completed in 3rd week of September 2011. |
|