Plants & Projects
 
125 MMSCFD Capacity Dehydration Plant at Mari Field
 
MGCL installed and commissioned 125 MMSCFD capacity Dehydration Plant at Mari D&P lease area in December 2009 to provide 109 MMSCFD to two “IPP” Independent Power Producers namely Foundation Power Company (Daharki) Limited and Star Power Generation Limited. The plant utilizes TEG as medium to remove moisture and is equipped with State of the Art PLC based control system. MGCL professionals are fully trained and equipped to achieve the set goal of on specification gas supply to its customers.

15 MMSCFD Capacity Dehydration Plant (Koonj-1A)

After discovery of Koonj Gas Field in 2008, as an operator of Sukkur Block MGCL obtained approval of EWT from GOP and started activities to bring this gas on production on fast track basis. Laying of 13 KM gas line, construction of surface facilities and installation of 15 MMSCFD capacity Dehydration plant was carried out after GSA with M/s SNGPL.

EWT operations commenced on January 28, 2010 after site acceptance test of Dehydration plant. EWT was suspended on February 20, 2010 due to unexpected increase of H2S contents in gas against permissible limit of agreed in GSA.

Joint Venture of the block after evaluating various options selected Amine Sweetening technique to reduce H2S concentration. Consignment has been received and its installation and commissioning is in final stages. It is expected that the EWT operation will resume in the last week of September 2011.

Bhit Shah X-1


MGCL offered drilling services of Mari Rig-1 to M/s PPL in Hala Block where it carries 35% working interest and won the contract in open bidding. This is the 1st ever venture of MGCL to work as drilling contractor outside MGCL operated blocks. The well has reached it TD @ 3730 m on August 09, 2011. The well is under logging and testing.

Halini X-1

MGCL as an operator with 65% working interest in Karak Block with MOL (Joint Venture partner with 35% interest) is in final stages of drilling / testing of 5350 meter well. The TD has been achieved in 201 days with Schlumberger Rig-25. Testing of various promising zones shall be completed in 3rd week of September 2011.